Aviation Budget Hearing Debrief: Global Terminal CMR, Budget and Concessions
At the Oct. 27 Budget Committee hearing, Aviation Commissioner Mike McMurray testified. Per the hearing transcript, no alderman asked about a Global Terminal Construction Manager at Risk (CMR) selection or decision, and the Global Terminal came up only in the Commissioner’s own remarks. No public City document we found names a CMR for the Global Terminal. The proposed 2027 Aviation budget is about $1.78 billion all funds, and ORDNext is $8.8 billion by the City’s figure.
1. Bottom line
- Global Terminal CMR (Construction Manager at Risk): per the hearing transcript, no alderman asked about a Global Terminal CMR selection or decision, and nothing about one was said. The Global Terminal came up only in Commissioner McMurray’s own remarks (his opening statement and a reply to a member’s question). No City release, ORD21 page, Council filing or news story we could open names a CMR for the O’Hare Global Terminal (OGT) or says a selection is pending. See Section 3 for the nearest public documents.
- “CMR” means Construction Manager at Risk in this program. The City’s O’Hare 21 contractor guidebook is titled “Doing Business with a Construction Manager at Risk,” and the City’s other documents use the abbreviation CMAR. Same thing.
- One CMAR question was asked, about the program in general. Ald. Michael D. Rodriguez (22nd) asked whether the CMAR work for ORDNext “has been working out okay.” The Commissioner answered “It has” and cited Concourse D as on scope, on schedule and under budget (Section 2).
- Budget: the proposed 2027 Aviation budget is about $1.78 billion all funds, up 6.9% (BGA), or about $1.013 billion in airport enterprise-fund appropriations ($826.3M O’Hare, $186.9M Midway) in the City’s recommendation.
- Terminal program: the City’s figure for ORDNext is $8.8 billion ($8.78B in the June release). The Global Terminal is scheduled for construction 2029 to 2033. No Global Terminal cost figure was given at the hearing.
- Concessions: per Crain’s, winners of the 21-package Terminal 1 and Terminal 3 ORDer Up! program are expected “any day,” with contracts to Council in 30 to 45 days.
Reading the sources: the hearing transcript is automatic captions with no speaker labels; speaker names below come from the Chicago Politics meeting notes (AI-written, speakers inferred) and should be confirmed on video. We could not open the Crain’s Oct. 27 article (it returned HTTP 403), so Crain’s details are carried from our concessions memo.
2. What was said at the hearing
Hearing: Chicago City Council Committee on Budget and Government Operations, Infrastructure Day 1, Tuesday, Oct. 27, 2026, 9:30 AM CT (Buildings, Aviation, Fleet and Facility Management, Environment). Aviation Commissioner Mike McMurray testified. The Aviation segment starts at about 2:47:13 in the transcript.
Global Terminal and CMAR
- Global Terminal CMR selection or decision: no alderman asked, and no one said anything about it. A search of the whole transcript for “CMAR,” “CMR,” “construction manager at risk” and “Global Terminal” found nothing on a Global Terminal CMR assignment, procurement or delay.
- CMAR in general: Per Chicago Politics, Ald. Rodriguez asked at about 5:04:02 about the concessions evaluation process and “CMAR construction performance.” In the transcript he asks the Commissioner whether work under “CMARs, your construction managers at risk” for ORDNext “has been working out okay.” The Commissioner: “It has.” He cited Concourse D, “about a $1.4 billion, $1.5 billion project,” as “on scope, on schedule… under budget,” and said that shows “it’s working.” Ald. Rodriguez also asked about a Concourse D concessions RFP; the Commissioner said one is coming because Concourse D opens in Q4 2028.
- Global Terminal mentions (all from the Commissioner; no questions on it):
- Opening statement: Concourse E ($917M, 14 gates by 2030) “will create the capacity we need to build the O’Hare Global Terminal… in a single coordinated phase, with construction beginning in 2029 and completion scheduled for 2033.”
- Concourse D: “at least $21 million below the approved budget.”
- In a reply to a member (Ald. Lopez, per the Chicago Politics notes), he called the Global Terminal the “crown, the centerpiece of the ORD Next,” said no sketches have been released yet, and said he hopes to have “schematics or drawings” to show the Council and the public “sometime very soon.”
- Ald. Nugent asked about ORDNext design and art (per the notes); the Global Terminal is not named in her question.
- Cost: no Global Terminal cost figure was given. Only the $8.8B ORDNext program, Concourse D at roughly $1.4B to $1.5B (Commissioner, in the transcript) and Concourse E at $917M.
- Aviation budget questions: Ald. Dowell asked about the contractual-services increase. The Commissioner said part is IT-related and mentioned digitizing “terminals one, three, and five.”
Concessions (consistent with the Crain’s report)
| Item | Source |
|---|---|
| Winners of the 110-location, 21-package Terminal 1 and Terminal 3 concession contracts expected “any day”; contracts to Council in 30 to 45 days; 167 proposals; evaluators include a law firm and Unison Consulting | Crain’s Chicago Business, Oct. 27, 2026 (article not opened by us; carried from our concessions memo) |
| Ald. Beale (9th) asked about the review process and outside influence, and asked that the consultants appear when contracts come to committee | Chicago Politics notes and transcript; Crain’s |
| Ald. Conway, Lawson, La Spata and Rodriguez asked about the RFP | Chicago Politics notes |
| The Commissioner said he is waiting on award recommendations, then a negotiation period, then will send his recommendation to the Aviation Committee and then Council | Transcript |
| Chicago Bars reported on X that the Commissioner said applicants’ original information needs re-verifying because of the delay | https://x.com/chicagobars/status/2115166178608075039 |
Hearing-record watch: after each hearing, departments usually answer members’ questions in writing, and the City posts opening statements and responses on the OBM budget-hearings page. As of Oct. 28 that page lists only prior-cycle (Oct. 2025) Aviation items.
3. Global Terminal CMR: what the public record says (nearest documents)
Plain statement: no public document we found names a CMAR for the Global Terminal, announces a CMAR selection process for it, or reports a CMAR “decision” being made or delayed.
Nearest documents:
- May 2019 City release (3 CMAR contracts, $116M each: Austin Power Partners, Turner Paschen Aviation Partners, AECOM Hunt Clayco JV). Procurement was an RFQ in March 2017 (7 respondents) and an RFP in Oct. 2018 (5 respondents). The release says CMAR scope “has not been divided out yet” and will include Terminal 5, Satellite Terminal 2 and the APM tunnel, mass grading, and “various projects that will enable the construction of future O’Hare 21 projects such as the O’Hare Global Terminal and Global Concourse.”
- ORD21 business-process page now lists five CMARs: AECOM Hunt Clayco Bowa (AHCB), Turner Paschen Aviation Partners, Austin Power Partners, Clark-O’Neil T3 Partners (COT3) and Power Construction Company. It does not map any of them to the Global Terminal.
- City contract record (PO 98447, AECOM Hunt / Clayco JV, CMAR services for O’Hare 21) shows an Oct. 20, 2025 modification of $1,720,000,000 and a June 30, 2026 modification extending the contract end date to May 22, 2027. This is a program-wide record and does not say Global Terminal. (Read from a search-index copy of the page; confirm on the live page before citing.)
- June 26, 2026 City release: AHCB is the lead contractor for New Concourse D under a $1.455B Guaranteed Maximum Price, reached under the CMAR delivery model. The release describes the broader program as including “the new O’Hare Global Terminal” but names no Global Terminal CMAR.
- Concourse E bidding is run by AHCB (public bid notices; Concourse E Trade Package 15, electrical, shows prequalification and bids due Nov. 12, 2026, with a description that includes the tunnel connecting Concourse D and the future global terminal). This shows who is procuring Concourse E trade packages. It does not show who will build the Global Terminal.
- Aug. 20, 2026 City release: Global Terminal to be built in “a single, coordinated phase beginning in 2029,” complete 2033.
Reading (inference, not a City statement): the City has multiple CMARs under contract and the Global Terminal scope was not publicly allocated in the documents above. Any claim of a Global Terminal CMR “decision” is unconfirmed until the City, ORD21 or a Council filing says so.
How to close this gap: (a) watch the Oct. 27 video and the Aviation written responses when posted; (b) ask CDA or the Connect Chicago Alliance PMO how OGT will be delivered and when any CMAR scope for it will be assigned; (c) watch the Aviation Committee and full Council agendas for any CMAR contract amendment ordinance; (d) check the CDA Procurement Opportunities Guide for a refreshed forecast (the version we found runs through 4Q 2025).
4. Short timeline
| Date | Event | Source |
|---|---|---|
| Mar. 2017 / Oct. 2018 | CMAR RFQ (7 respondents) and RFP (5 respondents) | chicago.gov, May 2019 release |
| May 2019 | Three CMARs awarded, $116M each; Global Terminal scope not yet divided | chicago.gov |
| Feb. 2024 | Crain’s reports Global Terminal estimate cut from $2.10B to $1.83B inside a revised $6.1B terminal project (older estimate; not the current program figure) | Crain’s via Internet Archive |
| Nov. to Dec. 2025 | City bond statement says it is negotiating a new sequence; Sun-Times reports Global Terminal 2029 to 2033 | Chicago Sun-Times, Dec. 2, 2025 |
| Feb. 6, 2026 | Crain’s: Commissioner expected concession awards to begin by end of March 2026 | Crain’s |
| June 26, 2026 | Concourse D GMP $1.455B, at least $21M under budget (AHCB) | chicago.gov |
| Aug. 20, 2026 | Resequence: D late 2028; E Phase 1 (14 gates) opens 2030; Global Terminal 2029 to 2033; E Phase 2 (10 gates) 2034; $8.8B | chicago.gov |
| Oct. 26, 2026 | BGA publishes Aviation 2027 budget snapshot | BGA |
| Oct. 27, 2026 | Aviation budget hearing; Crain’s concessions story | Hearing transcript; Crain’s |
| Nov. 9, 2026 | Budget hearing for Procurement Services | Chicago Politics schedule |
| Nov. 12, 2026 | Concourse E Trade Package 15 prequalification and bid due (listing) | InstantMarkets listing |
| Dec. 8, 2026 | Council public hearing on the budget, 11:30 AM CT | R2026-0029546 per Chicago Politics |
| Dec. 31, 2026 | City must pass a budget | Chicago Politics |
5. Key numbers with sources
| Number | What it is | Source |
|---|---|---|
| $1,781,779,989 | Aviation 2027 proposed appropriations, all funds; +6.9% (+$115,686,460) vs 2026 | https://chicagobudget.bettergov.org/2027/chicago-department-of-aviation/ |
| 2,476 | Budgeted positions, up 33 (+1.4%); includes 5 added Project Manager positions; 14.1% average vacancy Jan. to Sept. 2026 | same BGA page |
| +$237.3M (+56.6%) | Increase in outside contracting (professional and technical services) appropriation | same BGA page |
| $403.31M vs $524.53M | FAA AIP grant appropriation for O’Hare, 2027 vs 2026 | same BGA page |
| $100.545M vs $32.154M | IDOT Aviation Fuel Tax Program, O’Hare, 2027 vs 2026 | same BGA page |
| $1.013B | CDA enterprise-fund appropriations in the recommendation: O’Hare $826.3M (up $86.6M from $739.7M revised 2026), Midway $186.9M (up $7.1M) | FY2027 Budget Recommendations, via our Oct. 21 debrief |
| $8.8B ($8.78B) | ORDNext program, City figure; funded by airport revenues, “no state or local taxpayer dollars” per City | https://www.chicago.gov/city/en/depts/mayor/press_room/press_releases/2026/august/concourse-e-ohare.html and https://www.chicago.gov/city/en/depts/mayor/press_room/press_releases/2026/may/ord-under-budget.html |
| $1.455B | Concourse D Guaranteed Maximum Price (AHCB), at least $21M under budget | June 26, 2026 release (link above) |
| $917M | Concourse E, 14 gates by 2030 | Commissioner’s opening statement (transcript) |
| $1.83B | Feb. 2024 revised Global Terminal estimate (older; verify current figure) | https://web.archive.org/web/20240302083822/www.chicagobusiness.com/airlines-airports/chicago-proposes-major-spending-cuts-ohare-airport-terminal-project |
| 2.2M sq ft | Planned Global Terminal size, about twice Terminal 2 | https://aviationweek.com/air-transport/airports-networks/chicago-ohare-changes-construction-sequence-88b-revamp |
| 2029 to 2033 | Global Terminal construction window | Aug. 20, 2026 release |
| 21 packages; 167 proposals; 110 locations | ORDer Up! per Crain’s Oct. 27 | Crain’s (not opened by us) |
| 112 locations; 146,000+ sq ft | ORDer Up! RFP as issued Sept. 2024 | https://www.chicago.gov/city/en/depts/mayor/press_room/press_releases/2024/september/ConcessionsBidsOHare.html |
Number cautions:
- The two Aviation budget totals ($1.78B vs $1.013B) measure different things: all-funds appropriations (BGA) vs enterprise-fund appropriations (City recommendation). Do not mix them.
- Proposal counts differ by source: Crain’s Feb. 2026 reportedly said 107 (per Hoodline’s summary), the City’s 2025 legislative guide said “more than 165,” and Crain’s Oct. 27 says 167. Location counts: 110 (Crain’s Oct. 27) vs 112 (City 2024 release). Reconcile before quoting.
- The Concourse D $1.455B and the $8.8B are not additive to a Global Terminal figure. We found no current City-published Global Terminal cost.
6. Concessions (ORDer Up!)
- Per Crain’s (Oct. 27): award recommendations expected “any day”; CDA then negotiates and hopes to send contracts to Council in 30 to 45 days; evaluators include a law firm plus Unison Consulting.
- Our estimate: 30 to 45 days from Oct. 27 to 28 is roughly Nov. 26 to Dec. 12, 2026. Posted full-Council dates are Dec. 8 (budget public hearing) and Dec. 9. This is an estimate, not a City commitment.
- Slippage context: in Feb. 2026 the City expected to begin awards by end of March. “Any day” is soft.
- Global Terminal concessions: the City has said timing for Global Terminal concession solicitations has not been set. Concourse E materials say it will have “new dining and retail opportunities.”
- Not found: any public winner list; any protest.
See also our full ORDer Up! analysis.
7. Confirmed vs. unconfirmed
Confirmed (public documents and the hearing transcript):
- Aviation testified Oct. 27 at the Infrastructure Day 1 hearing.
- No alderman asked about a Global Terminal CMR selection or decision, and none was discussed in the transcript; the Global Terminal came up only in the Commissioner’s remarks.
- One general CMAR performance question (Ald. Rodriguez) and the Commissioner’s answer.
- 2027 Aviation budget figures in Section 5 (BGA; City recommendation as reported).
- $8.8B program; Concourse D GMP $1.455B with AHCB; Aug. 20 resequence and Global Terminal 2029 to 2033 (City releases).
- Five CMARs on the ORD21 roster; 2019 CMAR scope language naming Global Terminal enabling work.
Unconfirmed or not found:
- Any Global Terminal CMR selection, solicitation or decision date.
- Speaker identities in the transcript (inferred in the Chicago Politics notes; confirm on video).
- Crain’s Oct. 27 details (article not opened by us).
- Current City-published Global Terminal cost figure.
- Any concession winners or Council date.
8. What to watch next
- Hearing record: Oct. 27 video, CDA written responses (Councilmatic event page; chicago.gov OBM budget-hearings page; City Clerk video archive).
- Council agendas (Aviation Committee and full Council, Dec. 8 to 9) for concession leases or any CMAR contract amendment.
- CDA and ORD21 postings: an updated Procurement Opportunities Guide, a Global Terminal procurement notice, or any CMAR assignment.
- Concourse E bid packages (AHCB): Trade Package 15 due Nov. 12.
- The concessions awards announcement and the lease terms filed with Council.
- Nov. 9 Procurement Services hearing: general context on City contracting.
- Concourse D and Global Terminal schematics the Commissioner said he hopes to release “sometime very soon,” and later bond disclosures, which are the likeliest place for Global Terminal delivery details.
9. Gaps
- Crain’s Oct. 27 article was blocked (HTTP 403) from our tools; Crain’s details are carried from our concessions memo.
- The transcript is automatic captions with no speaker labels; names come from the Chicago Politics notes.
- ord21.com pages were blocked by Cloudflare from our fetch tool; ORD21 content here comes from search-index excerpts. Verify live.
- No Global Terminal CMR information found in any source.
- No current City-published Global Terminal cost found; the $1.83B is a 2024 estimate.
- No Oct. 27 Aviation hearing coverage found from Sun-Times, Tribune, WTTW, Block Club, Illinois Policy or the Daily Line as of Oct. 28.
Sources
- Chicago Politics, Oct. 27 Budget Committee meeting page and notes: https://www.chicagopolitics.org/meeting/851CA01E-91C9-F111-AAAE-001DD80B58E5
- Chicago Politics, hearing transcript (automatic captions): https://www.chicagopolitics.org/files/transcripts/1239662145.txt
- BGA Policy, Department of Aviation 2027 Budget Snapshot (Oct. 26, 2026): https://chicagobudget.bettergov.org/2027/chicago-department-of-aviation/
- City of Chicago, Concourse E first-phase release (Aug. 20, 2026): https://www.chicago.gov/city/en/depts/mayor/press_room/press_releases/2026/august/concourse-e-ohare.html
- City of Chicago, Concourse D GMP release (June 26, 2026): https://www.chicago.gov/city/en/depts/mayor/press_room/press_releases/2026/may/ord-under-budget.html
- City of Chicago, O’Hare 21 lead architect and CMAR awards (May 2019): https://www.chicago.gov/city/en/depts/doa/provdrs/omp/news/2019/may/-city-of-chicago-awards-lead-architect-and-construction-manager-.html
- ORD21, Understanding the Business Process (CMAR roster; CMAR method): https://ord21.com/bids/Pages/business-process.aspx
- ORD21, ORDNext page: https://ord21.com/Pages/ORDNext.aspx
- ORD21, CMR’s Guidebook: https://ord21.com/SiteCollectionDocuments/O%27HARE%2021%20DOING%20BUSINESS%20with%20a%20Construction%20Manager%20at%20Risk%20FINAL%20V2%20(5-20).pdf
- City contract record PO 98447: https://webapps1.chicago.gov/vcsearch/city/contracts/98447
- Chicago Sun-Times, Dec. 2, 2025: https://chicago.suntimes.com/transportation/2025/12/02/ohare-global-terminal-construction-american-united
- Aviation Week, Aug. 25, 2026: https://aviationweek.com/air-transport/airports-networks/chicago-ohare-changes-construction-sequence-88b-revamp
- Chicago YIMBY, Sept. 5, 2026: https://chicagoyimby.com/2026/09/new-timeline-and-details-revealed-for-ordnext.html
- Chicago Politics, budget hearing schedule (Oct. 24, 2026): https://www.chicagopolitics.org/on-my-block/chicago-budget-hearings-schedule-department-by-department-2027
- Councilmatic, Oct. 27 Budget Committee event: https://chicago.councilmatic.org/event/committee-on-budget-and-government-3774d333079b/
- City OBM budget hearings page: https://www.chicago.gov/city/en/depts/obm/provdrs/budget/svcs/BudgetHearings.html
- City Clerk, 2027 budget page (committee video archive): https://www.chicityclerk.com/2027-chicago-city-budget
- Crain’s Chicago Business, O’Hare concessions story (Oct. 27, 2026; not opened by us)
- Crain’s, Feb. 6, 2026 concessions: https://www.chicagobusiness.com/airlines-airports/city-moves-award-biggest-us-airport-concessions-deal/
- City, ORDer Up! release (Sept. 2024): https://www.chicago.gov/city/en/depts/mayor/press_room/press_releases/2024/september/ConcessionsBidsOHare.html
- Concourse E Trade Package 15 listing: https://www.instantmarkets.com/view/ID111384883250919080737684113667490980178
- Chicago Bars on X: https://x.com/chicagobars/status/2115166178608075039
- GOTB, Budget Day debrief (Oct. 21, 2026): https://gotbconsulting.com/city-council/2026-10-21-budget-day/
This debrief reflects public information as of Oct. 28, 2026. It is not legal advice. It draws no conclusions about any person or office, and quotations appear only as reported in the cited sources.